(€3bn project cost) Lean Construction

Lean Touch Solutions Limited successfully deployed Lean Construction & the Last Planner system over a 2 year period 2012 to 2015 delivering significant benefits to the project.

Trained in excess of 1500 trade partners on lean Construction & the last planner system before moving into our standard facilitation & mentoring across the Campus to implement the last planner system.

At the time of implementation this project was recognised by the Intel Global GM of Construction as best in class of any project in the Intel portfolio of projects globally.